Work intensity (man hours per m2)

Construction[None]Time

Definition

This KPI is calculated for new builds and repair and maintenance projects, but not for infrastructure projects. Besides, the work intensity is only calculated when the number of man hours is recorded for all contracts of relevance to a construction project. This means that the work intensity is calculated at project level and not for individual contracts. The work intensity is defined as the number of man hours worked by hourly paid labour per m2 total floor area. The work intensity is intende